Delivery times for transformer components

Standard delivery times from Ludvika, Sweden

The delivery times below reflect our general load situation. However, we reserve ourselves for large orders received during the period in between, which might affect actual delivery time. 

Shorter delivery times are also available but are subject to material availability. Please contact our Sales Department if the indicated delivery times do not meet your requirements and material availability. 

Please note that final delivery times are always as per the order acknowledgment.

Updated as of Oct 29, 2026

Present Preliminary Delivery Times

TAP-CHANGERS
UB 10 weeks
UZ 22 weeks
UCG 14 weeks
UCL 14 weeks
UCC/UCD on request
VUBB 10 weeks
VUCG 14 weeks
VUCL 14 weeks
BUSHINGS  
GOB+ 40 weeks
GOE ≤1675 27 weeks
GOE 1800 27 weeks
GOE ≤2550 on request
GOE 2600 on request
GOE(2) ≤1425 27 weeks
GOE(2) 1675 27 weeks
GOEK on request
GOH 46 weeks
GSA-OA/ARF AF/ED ≤170 40 weeks
GSA-OA/ARF AF/ED 245 40 weeks
GSA-OO 40 weeks
GSBK 135 weeks
ARF 245 135 weeks
ARF 300 135 weeks
ARF 362 135 weeks
ARF 420 135 weeks
ARF 550 135 weeks
ARF 765/800 on request