Delivery times for components (Hefei, China)

Remark

  • Validation: Till December 31st.
  • Standard delivery time refers to ex-works Hefei Hitachi Energy date with full order confirmation.
  • Any exceptional cases (urgent/big volume/special design orders) need to be further reviewed.

Type Standard delivery time
TOB 325, CT length <= 0.6 4 weeks
TOB 550, CT length <= 0.6 4 weeks
TOM 1050, CT length <= 0.6 4 weeks
TOB/TOM, CT length=0.8 11 weeks
TOB/TOM, on plateau areas 11 weeks
GOE On request
Dry bushing On request

Type Standard delivery time
UBB 4 weeks
UCG, <= 600 A 4 weeks
Tap changer with selector III on request
UCG, > 600 A 9 weeks
Tap changer with selector III on request
UCGRT 11 weeks
Tap changer with selector III or BUE2 on request
VUCGR(D/L)N 6-8 weeks
Tap changer with selector III on request
VUCGR(D/L)T 8-10 weeks
Tap changer with selector III on request

Type Standard delivery time
Standard type 8 weeks
Special type On request

Product family Standard delivery time
Air dehumidifier 30 days
Pressure release device 30 days
Oil level indicator 30 days
Buchholz relay & Oil relay 30 days
Gas sampling device 30 days
Porcelain bushing 120 days
HEDICO product 30 days
Import product On request