変圧器の構成部品の納期について
当社のタップ切換器とブッシングの納期については、それぞれ以下の生産拠点からご確認ください。
- Ludvika, Sweden
- Zurich, Switzerland
- Hefei, China
- Alamo, Tennessee, USA
Standard delivery times from Ludvika, Sweden.
The delivery times below reflect our general load situation however we reserve ourselves for large orders received during the period in between, which might affect actual delivery time.
Shorter delivery times are also available but is subject to material availability. Please contact our Sales Department if the indicated delivery times does not meet your requirements and material availability.
Please note that final delivery times are always as per the order acknowledgement.
Present Preliminary Delivery Times (Updated as of January 18, 2022)
TAP CHANGERS | |
UB | 7 weeks |
UZ | 7 weeks |
UCG | 6 weeks |
UCL | 6 weeks |
UCC/UCD | 15 weeks |
VUBB | 7 weeks |
VUCG | 6 weeks |
VUCL | 6 weeks |
BUSHINGS | |
GOB | 7 weeks |
GOB 1050 | 11 weeks |
GOE ≤ 1425 |
11 weeks |
GOE 1675 | 11 weeks |
GOE 1800 | 13 weeks |
GOE ≤ 2550 | 19 weeks |
GOE 2600 | 19 weeks |
GOE(2) ≤ 1425 | 14 weeks |
GOE(2) 1675 | 14 weeks |
GOEK | 26 weeks |
GOM | 11 weeks |
GOH | 6 weeks |
GSA-OA ≤ 170 |
11 weeks |
GSA-OA 245 | 16 weeks |
GSA-OO | 11 weeks |
GSB 245 | 16 weeks |
GSB 362 | 21 weeks |
GSB 420 | 21 weeks |
GSB 550 | 14 weeks |
GSB 800 | 15 weeks |
GSBK | 18 weeks |
AirRIPflex 300 | 14 weeks |
AirRIPflex 362 | 14 weeks |
AirRIPflex 420 | 14 weeks |
AirRIPflex 550 | 14 weeks |
Contact us