Delivery times for bushings and tap-changers (Ludvika, Sweden)

Standard delivery times from Ludvika, Sweden. Valid for delivery Ex-works Ludvika after full and firm order.

The delivery times below reflect our general load situation however we reserve ourselves for large orders received during the period in between, which might affect actual delivery time. If the indicated delivery times does not meet your requirements, please contact our sales department. Final delivery times are always as per the order acknowledgement.

Bushing delivery times are applicable for standard oil impregnated bushings with brown insulators and resin impregnated bushings with grey insulators and standard shed profile.

Shorter delivery times available, subject to material availability. Contact our sales department.

PRESENT PRELIMINARY DELIVERY TIMES - updated on January 2, 2023

 TAP-CHANGERS
 UB.. 8 weeks 
 UZ.. 7 weeks     
 UCG.. 6 weeks        
 UCL.. 6 weeks          
 UCC../UCD... 15 weeks    
 VUBB.. 8 weeks       
 VUCG.. 6 weeks          
 VUCL.. 6 weeks
 BUSHINGS
 GOB 14 weeks
 GOB 1050 14 weeks 
 GOE ≤ 1425 11 weeks  
 GOE 1675 11 weeks 
 GOE 1800 13 weeks 
 GOE ≤ 2550 15 weeks
 GOE 2600 15 weeks
 GOE(2) ≤ 1425 11 weeks 
 GOE(2) 1675 11 weeks 
 GOEK 26 weeks 
 GOM 11 weeks
 GOH 8 weeks 
 GSA-OA ≤ 170 14 weeks 
 GSA-OA 245 15 weeks
 GSA-OO  14 weeks 
 GSB 245 23 weeks
 GSB 362 26 weeks 
 GSB 420 24 weeks 
 GSB 550 19 weeks 
 GSB 800 16 weeks
 GSBK 21 weeks
 ARF 245 24 weeks
 ARF 300          24 weeks
 ARF 362          24 weeks
 ARF 420          24 weeks
 ARF 550         
19 weeks